This project was carried out in two phases.  The first phase required the construction of a new extension to the existing school building providing two new classrooms, WC’s, storage space and break out areas with associated external works.  Works included the installation of bespoke windows including a stained glass window that was designed by the school pupils.

Phase 2 involved the construction of a stand alone new play group building incorporating nursery facilities and office space.  The new areas were fitted out and all associated external works and landscaping completed the project. 

The project was delivered on time and within budget and was awarded a certificate of compliance under the Considerate Constructors scheme.

 

Client: West Sussex County Council
Value: £800,000
Duration: 44 weeks